The Cole Creek restoration plan
Lake County is planning a restoration of Lower Cole Creek that aims to reduce flooding in Green Acres and help Clear Lake hitch. This page tracks where the project stands, using public records and our own updates. We'll keep it current as the work moves along.
Last reviewed October 23, 2026.
Where things stand
- Design funding
- CDFW grant of up to $500,122. FlowWest contract of $349,647.
- Design deadline
- March 1, 2028, when the grant and contract end.
- Construction funding
- Not identified yet.
- Latest creek maintenance
- County sediment removal, October 2026.
- Advisory Collaborative meetings
- Third Friday of every month, by invitation.
What the project is for
The county's agreement with FlowWest describes the goal as
design drawings for an implementation project to reduce flooding and improve habitat conditions for Clear Lake hitch.
The county's request for proposals covers about 1.55 miles of Cole Creek. For years, sediment has filled the channel, so storm water spills onto nearby land and stays there. Hitch that swim up the creek to spawn get stranded in the flooded fields. One project can address both problems.
FlowWest has just started, and the specific work will come out of their planning. We'll add details here as they're shared.
Steps to a lasting fix
-
1.
Fund the planning and design
Done June 2025The California Department of Fish and Wildlife awarded the Lake County Watershed Protection District up to $500,122 to plan and design work on Cole Creek. Read more
-
2.
Hire a design team
Done August 2026After a public request for proposals, the Board of Supervisors approved a $349,647 agreement with FlowWest. Read more
-
3.
Plan and design the restoration
Underway Through March 1, 2028FlowWest has started work. The scope, schedule, and public meetings are being worked out now. The goal is a design that is ready to build.
-
4.
Find money to build it
Needed Not identified yetThe current grant and contract pay for planning and design only. Construction needs its own funding.
-
5.
Build the project
Not started Not scheduledConstruction can start once the design is finished, permits are in place, and funding is found.
What we're asking
These are the questions we bring to the county and its partners, with the best answer we have today.
- What work will address the flooding and help fish get through the creek?
- The FlowWest agreement aims to reduce flooding and improve habitat for Clear Lake hitch in Lower Cole Creek. The specific work will come out of the planning now underway.
- What money is available, and what else is needed to get the work done?
- Planning and design are funded through March 2028. Money to build the project has not been identified.
- Who's handling each step, and when should we expect it?
- The Lake County Watershed Protection District leads the project and FlowWest is doing the design. A schedule has not been published yet.
- Will the channel be kept clear until the project is built?
- The county cleared debris and sediment in 2025 and 2026. We'd like to see that maintenance planned every year until construction is done.
Timeline
-
Late 1950s
Cole Creek is straightened and a levee is built near Clark Drive.
-
February 2023
The Board of Supervisors declares a Clear Lake hitch emergency.
-
May 2023
After months of standing water, CDFW authorizes emergency clearing of a blocked culvert.
-
October 2023
-
August 2024
Agencies, Big Valley Rancheria, and neighbors start meeting monthly about the creek.
-
January 2025
The U.S. Fish and Wildlife Service proposes listing Clear Lake hitch as threatened.
-
Winter 2025
A Pharo Place pasture stays flooded for at least 135 days, peaking at 2.31 feet.
-
January to April 2025
-
June 2025
CDFW awards the District up to $500,122 for Cole Creek planning and design.
-
August 2025
County crews clear vegetation and sediment upstream of Clark Drive Bridge.
-
September 2025
The county asks for proposals to plan and design 1.55 miles of Cole Creek.
-
December 2025
California Conservation Corps crews clear vegetation from the channel.
-
Winter 2026
With similar rainfall, the same pasture peaks at 0.40 feet and drains within days.
-
April 2026
The Center for Biological Diversity sues to force a final decision on protecting the hitch.
-
May 2026
The county selects FlowWest for the planning and design work.
-
August 2026
The Board of Supervisors approves a $349,647 agreement with FlowWest.
-
September and October 2026
-
March 1, 2028
Planning and design grant and contract end.
Who's involved
- Lake County Watershed Protection District and Water Resources
- Leads the project, manages the grant and contract, and maintains the channel.
- FlowWest
- Planning and design contractor.
- California Department of Fish and Wildlife
- Funds the planning and design and permits work in the creek.
- Big Valley Band of Pomo Indians
- Partner in monitoring and planning.
- State Water Resources Control Board
- Partner in water level monitoring at Pharo Place.
- O'Connor Environmental
- Runs the Pharo Place water level sensors.
- U.S. Fish and Wildlife Service
- Deciding whether to list Clear Lake hitch under the federal Endangered Species Act.
- Green Acres neighbors
- Document conditions, share local knowledge, and take part in planning.
Agencies, Big Valley Rancheria, FlowWest, and neighbors meet on the third Friday of every month as the Cole Creek Advisory Collaborative. Participation is by invitation. If you work on the creek or have a stake in it and would like to take part, email mail@colecreekflooding.com.
Sources
-
FlowWest agreement, Lake County file 26-0761
Board of Supervisors, sitting as the Watershed Protection District board, August 4, 2026. $349,647, July 31, 2026 to March 1, 2028.
-
CDFW grant resolution, Lake County file 25-880
Includes CDFW's June 25, 2025 notice of award for up to $500,122.
-
Request for proposals No. 251355
Task C: Cole Creek planning and design for 1.55 miles of creek.
-
Two winters at Pharo Place
Water level monitoring results and full report.
-
Proposed federal listing of Clear Lake hitch
Federal Register, January 16, 2025.